The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Velocity chart

Paulina Mijal
November 2, 2022

Dear all, 

I have a question. If we add some estimated task after starting a sprint (as scope change), it will be includeed?

2 answers

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Trudy P Claspill
Community Champion
November 2, 2022

Hello @Paulina Mijal 

The Velocity Chart shows you the commitment  at the moment the sprint is started, and the completed work at the moment the sprint ended. It is looking at all issues in the sprint at those two moments.

Changing the scope of work after the sprint starts will not affect the Committed metric for the sprint. All issues in the sprint will be considered for the Completed metric at the end of the sprint; it doesn't matter if the issue was added after the start of the sprint or if the scope for an issue already in the sprint changes.

https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-velocity-chart/

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 2, 2022

Yes, scrum reports will show scope change.