The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Velocity Chart in JIRA Agile displaying incorrect velocity?

Miguel De Dios
February 17, 2014

I've looked at the data and so have a few other folks and 81 Commitment makes sense, but we still can't figure out how JIRA Agile reports 60 for completed in the Sprint: Rice Lake

After doing the math multiple times we've concluded that the true velocity is 51 not 60.

Burndown Chart followed by the Sprint Report for Sprint: Rice Lake

2 answers

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Rekha Bhaskaran
July 20, 2015

hi ,

Did you get any solution for this ?

0 votes
Miguel De Dios
February 17, 2014

I can send the images separately in an e-mail, I didn't think they would look that small after previewing. Sorry about that