The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Velocity Chart does NOT show all sprints

Fernando.Reich
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 19, 2023

Good Morning,

My Velocity Chart doesn´t show all sprints, for example, sprint 7 is not shown and also the sprints are not in the correct order.

I´m the project admin but I´ve tried to disable “Hide unrelated sprints viewing option from the Velocity Chart, but that option is not there  :-)

Does anyone know why some Sprints may not show up and how to fix the Order of Sprints in the Velocity Chart?

3 answers

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Valeriia_Havrylenko_SaaSJet
Atlassian Partner
February 5, 2024

Hi @Fernando.Reich @Brad Paugh   👋

With my SaaSJet team, we built a new Sprint Performance Report where we have all the metrics for each sprint. One of them is Team Velocity. Report available throw the Time In Status for Jira add-on. 

SP TV (1).png   

I would be happy if you had a look at it! 

Try Time In Status for Jira + Sprint Report for free.

You can also book a live demo - we'll show you the application inside out and answer all your questions.

Have a nice day and happy sprinting 🥳

1 vote
Trudy P Claspill
Community Champion
April 19, 2023

Hello @Fernando.Reich 

Welcome to the Atlassian community!

Velocity Charts will not show "all" sprints. They show only the last 7 sprints completed by the team. I have not played with this report much, but I would assume the selection of sprints and the ordering of them would be based on the Completion Date of the sprints that were created in the board where the report is being generated.

The "Hide Unrelated Sprints" option is available only in Jira Server/Data Center, not in Jira Cloud.

More information about the Velocity Chart can be found here:

https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-velocity-chart/

Brad Paugh
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 5, 2024

This is absurd, why would the hide unrelated sprints option only be on Jira server? The current velocity chart on Jira cloud is so limited it is useless. There are zero filtering options, and currently I can see hardly any of my team's recent sprints because it's full of other team's sprints.

Like Sylvie likes this
0 votes
Sarvesh Lowanshi
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 23, 2025

.

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
TAGS
AUG Leaders

Atlassian Community Events