The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Using blk edit can we add a epic to multiple issues?

sagireddy_reddy
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 10, 2026

i have 300 issues which needs to be linked to an epic , can we use bulk edit for this i cant see the option to edit linked issuesbulk edit pic.png

3 answers

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

2 votes
Karan Sachdev
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
April 10, 2026

Hey @sagireddy_reddy

Welcome to the Community!

On the bulk edit screen, you may search for Parent field instead of the Linked Issues field.

You can update the Parent field to the target epic, and complete the bulk operation. This should fulfil your requirement.

I hope this helps!

Thanks!!

1 vote
Peter_DevSamurai
Atlassian Partner
April 10, 2026

Hi @sagireddy_reddy , 

In Jira Cloud (including Enterprise), you cannot use bulk edit to add / change issue links (including “is parent of / is child of”), so that’s why you don’t see an option to edit Linked issues in the bulk change screen.

This is a known product limitation so for now, you can help upvote this request via JRACLOUD-2428. and hopefully, the Atlassian team will support this soon.


So for now, there are 2 options:

1) Use the backlog / board to re‑parent in bulk

If your issues are on a board that shows an Epic panel:

  1. Open the board backlog.

  2. Make sure the Epic panel is visible.

  3. Select the 300 issues (Shift‑click to select a range).

  4. Drag them onto the target epic in the Epic panel.

2) Since you’re on an Enterprise plan, you can also use Plans:

  1. Add those 300 issues into a plan.

  2. In the Scope section, select the issues you want to change.

  3. Use Bulk actions → Parent to set the same epic as their parent.

 

I hope the below documents are helpful for your case:

-> This updates the Parent field (i.e., sets the epic) for all selected issues, and then syncs back into Jira.

 

I hope everything works out well for you. 

Best regards,

Peter

0 votes
M Chandra Shekar
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 10, 2026

Hi @sagireddy_reddy  are the 300 issues child’s of epic? If yes you can choose parent or epic link column to map parent to 300 issues.

Comments for this post are closed

Community moderators have prevented the ability to post new answers.