We are trying to use the Capacity View in Advanced Roadmaps (Plans) to manage team and user capacity. We add the effort estimate under the "Original Estimate" field in hours, and set the Start Date and Due Date on the issues.
We would like to be able to pull the work items into a plan and see the capacity of a given team (and team members), based off the Duration (Start Date / Due Date) and effort (Original Estimate) in hours.
Can anyone provide some additional guidance on how the Capacity Planner in Plans rolls up a teams capacity when the effort is estimated in hours? Or what fields need to be populated in order to accurately use the capacity planner? We have tried working with the "remaining estimate" field but haven't been able to get this to populate.