The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

User Storys in the past

Max
June 6, 2024

Hello everyone,

I originally managed my Scrum project in an Excel.
I would now like to transfer these sprints from the past to Jira.
However, when I set the user stories to completed, they are displayed with the current date in the burn down chart.
How can I manually set the date when the user stories originally were completed?

Best regards,
Max

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Trudy P Claspill
Community Champion
June 6, 2024

Hello @Max 

Welcome to the Atlassian community.

Is this basically the same question you asked 6 hours ago?

https://community.atlassian.com/t5/Jira-questions/User-Stories-Epics/qaq-p/2719796