Is it possible to create a filter to show the last 10 tasks that have been updated within a project?
Community moderators have prevented the ability to post new answers.
No, filters don't have anything to say about the output of what they find, apart from the order which only gets used in a couple of places.
You can run a filter like "Project = x order by updated" and the issue navigator will list them for you, but there's no limit of 10.
Although you could put that same filter into a "filter results" dashboard gadget - they do list "the first x issues"