Update epic due date when child due date changes (Automation)

Lucy Cookney
Contributor
November 6, 2025

Hi

Can anyone tell me where I'm going wrong with this automation rule? It isn't even attempting to run. Could it be because I am updating the child due dates via a different automation?

Screenshot 2025-11-06 121304.png

Edit: It works fine when you manually add the due date to the child so it is because I'm updating it via automation - any way to get around this?

1 answer

1 accepted

0 votes
Answer accepted
Gor Greyan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 6, 2025

Hi @Lucy Cookney

Yes, if you are using another automation for updating the due date, you should put the following checkbox in order to allow another automation to run this one.

Screenshot 2025-11-06 162657.png


Lucy Cookney
Contributor
November 6, 2025

Oh amazing! I completely missed that option. Thank you :)

Like Gor Greyan likes this
Gor Greyan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 6, 2025

Dear @Lucy Cookney

You are very welcome.