Two teams Product and Engineering Backlog

Nikhil
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 16, 2017

I have two teams, Product and Engineering. I need to setup two agile sprints for both the teams. But as the story in the product sprint is completed it should be created as a backlog in the Engineering Board

How to handle this?

1 answer

0 votes
Peter DeWitt
Community Champion
October 16, 2017

@Nikhil, you'll need a workflow extension to do this.  Not sure it's the best idea to move the issue from one sprint to another though.  It may be better to create a new issue in the next sprint once the first is closed.  Something like Bob Swift's create on transition would work. 

-pd