My board (team-managed project) has estimation set to "Original estimate" (time tracking). Issues in the sprint have original estimates filled in (e.g., 1 hour on SCS-59).
Two problems:
1. The Sprint Insights panel burndown chart does not reflect these values. It appears to default to story points regardless of the board's estimation setting.
2. The active sprint board does not show a total estimate for the sprint, despite issues having original estimates.
Board ID: 240
Project: SCS (team-managed)
Site: hdip-aws-migration.atlassian.net
Expected: Burndown chart and sprint header use Original estimate values
Actual: Both show nothing / default to story points
Is this a known limitation or a bug?
This behavior is a known limitation in Jira Cloud’s team-managed projects rather than an isolated bug with your specific board.
Even though Atlassian allows you to switch your estimation feature to "Time" inside a team-managed project, several built-in agile reporting and board UI metrics are hardcoded to look exclusively for Story Points or Issue Count.
I belive this was answered here:
Configure how your board estimates and tracks work
don't forget to click the Accept Solution button