I have set up 2 projects, both have the same settings for issues & timelines. With one, I can see what I want - the individual issue dates when I expand, the other only blocks out with the epic timeline, how can I set this one to give the same individual date info?
Thanks
Hello @William Oakley
Welcome to the Atlassian community.
When viewing the timeline, click on the 3-dots button in the upper right corner and select Configure Timeline.
That should take you to a screen that looks similar to this. Please let us know what the settings are for each of the timelines.
If you have selected "Schedule by sprint dates" change the selection to "Schedule by start and due dates"