Timeline hides completed issues

Nikita
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 6, 2025

Hello 
In Advanced roadmap timeline, completed issues disappearing 30 days after completion. How to keep them?

1 answer

2 votes
Trudy Claspill
Community Champion
October 6, 2025

Hello @Nikita 

Welcome to the Atlassian community.

Go to Plan Settings.

Screenshot 2025-10-06 at 8.16.12 AM.png

 

Select Work In Your Plan and then select the Removed Work Items tab.

Screenshot 2025-10-06 at 8.17.41 AM.png

 

Click on the View Rules option in the box that says "Based on type or status" , and a panel will appear on the right where you can set the time period for hiding Done items.

Screenshot 2025-10-06 at 8.19.36 AM.png

 

 

Nikita
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 6, 2025

@Trudy Claspill You are the best! 
Thank you, all works 👍

Trudy Claspill
Community Champion
October 6, 2025

You're welcome!

If you question has been adequately addressed, please consider clicking on the Accept Answer button above my response to mark your Question as Solved. That helps others searching the community find the posts with validated responses.