The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Timeline Doesn't Show Green/Blue/Grey

Michael P_ O_Hara
August 16, 2024

Hi 

Is there any way to change the formatting to reflect the tasks done vs. in progress vs. to-do in the Timeline view?    Per below mine only show a single color rather than the more helpful view (i.e. top-level should show 2 of 8 in green)

 

Jira Timeline.jpg

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Trudy P Claspill
Community Champion
August 16, 2024

Hello @Michael P_ O_Hara 

No, that is not possible with the native functionality. The bar in the timeline is one solid color that reflects the status of the individual issue.