Hello All,

When I access one of my projects, its defaulting to the issues screen instead of the board. The Timeline, Backlog and Active Sprints are somehow hidden from the dashboard and I can no longer manage the sprints. from my PC. 

Ironically, all my other projects are working fine even-though they all share the same permission scheme. It gets even weirder because I can access the sprint board for the above mentioned project using the Jira app in my phone. The issue is only there in the desktop version. Please share any insight you have on this matter. 

SF Issue.png

1 answer

1 accepted

2 votes
Answer accepted
Nelphy Rose Siby October 24, 2023

This is resolved now.. Someone changed the board settings and added my project's board to another project by mistake. 