Hi there, I have configured the Time Tracking field in the story issue so that the time spent is logged in hours.
If I log time by accessing it from the story fields, the UX I get shows: Time Spent and Time Remaining.
Additionally, I have configured a screen associated with a specific transition status, which includes tracking, but the fields that appear for input are different: Original Estimate and Remaining Estimate.
I would like to configure the screen to display Time Spent and Time Remaining instead of Original Estimate and Remaining Estimate.
Thanks in advance
Hello @Roberto Tena
Welcome to the Atlassian community.
You need to add the Log Work field to the Transition screen to have it display the fields for logging time against the issue.