The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
  • Community
  • Q&A
  • Jira
  • Questions
  • The original time estimation of the parent story doesn't sum up for the total time of sub tasks

The original time estimation of the parent story doesn't sum up for the total time of sub tasks

Harshi Samarasekera
August 9, 2021

The original time estimation of the parent story doesn't sum up for the total time estimations of sub tasks. How to activate this?

example:

Story - A

Sub task - a1 - Original time estimation: 2h

Sub task - a2 - Original time estimation: 1h

After manually entering these time estimations in the sub tasks, why doesn't it get automatically added to the Original time estimation of Story A as 3h? How can I get this done?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Lisa Grau
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
August 10, 2021

Hi Harshi,

there should be a checkbox in the parent task right beneath the time tracking which states something like "Include sub-tasks".

You need to check the box, then the sub-tasks time will be added to the parents time tracking.

 

2021-08-10 09_09_04-LIZSW Board - Agile Board - Jira.png

(Zeiterfassung = Time-tracking)

DEPLOYMENT TYPE