The automation rule for auto update of start date for story from minimum start date of sub task is g

Vimal G July 23, 2025

The automation rule for auto update of start date for story from minimum start date of sub task is getting passed but the start date field is updating the date. why it is so

 

Please refer the screenshots

 

Start date rule 1.jpg

Start date rule 3.jpg

start date rule 2.jpg

 

The start date field is not getting updated. 

 

Please tell me the solution to get the date in the field

 

1 answer

2 votes
Walter Buggenhout
Community Champion
July 23, 2025

Hi @Vimal G,

Smart values are case sensitive. I see that you are trying to set the Start date (with a capital 'S', but you are using small letters in your smart value. Also, you would normally reference the result of your Lookup Work Items action as {{lookupIssues.xxx}} and not lookupIssue

Try updating it to:

{{lookupIssues.Start date.min}}

Hope this helps!

 