I would like to use Tempo to plan work for 80 people on a software development team. I need some help with best practices.
1) I have specific requirements like managing part time resources - how do I set workday different for each user.
2) How to plan time that is initially to a team and then to an individual. I have specific reporting requirements that include viewing capacity / plan - overall, at a team and at an individual.
Please suggest the best resource to assist with setup and reporting.
Thanks!
Community moderators have prevented the ability to post new answers.
Hi Brad,
1) Have a look at the Workload Schemes in Tempo to configure each user differently.
2) It is currently not possible to create a plan without specifying a user. Please track this issue for status.
Cheers,
Viðar