Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Tempo - Planning by timeline or Resource and impact on Capacity Report

Haydn Reece
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 14, 2020

Hi, 

A few weeks ago when Planning by timeline was down, I added planning by resource instead.

 

The issue is that now, when I run the capacity report it seems to ignore time that I added by resource, even though I can see the hours in the timeline view.

 

EG: These three team members are fully booked for week 17

https://www.screencast.com/t/pkL9CNeRi

 

However, in capacity report, the first two are showing as only having 1 hour booked

https://www.screencast.com/t/dDpvrDr9ZHnB

 

Does the capacity report not take into account time planned using "planning by resource"? 

 

If so, will I have to delete all and re plan by Timeline to see a true capacity? Also, given that I was told last year that Planning by Timeline was going to be phased out, is there a plan to have a similar tool added to "planning by resource"?

 

Thanks

 

 

0 answers

Suggest an answer

Log in or Sign up to answer