The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Tempo: Actual Vs Planned time

Randika Palipane
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 9, 2022

Hi Everyone, 

Is there a method/report available to filter, Billable work hours down to 3 levels; Project wise, User wise, Task to monitor Planned vs Actual?

 

Ex-

Project name

     User1

          Task 1

          Task2

     User2

          Task1

 

thanks, 

Randika

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
carolyn french
Community Champion
March 9, 2022

Hi @Randika Palipane ,

You can group by Epic in Planned vs Actual Report, however, I think the view you are looking for is actually in the Logged Time Report. You can add the columns Planned time, Billable time, and Logged time to your report, and then group by those 3 parameters- Project, User, Task.

You can click the top of the Billable column to sort to see the ones with billable time at the top. Alternatively, if you are using Billable Accounts, then you can filter by those Accounts.

Here's what it could look like. Make sure you enable the extra columns to show up:

Tempo Report - Logged Time Report.png

Randika Palipane
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 9, 2022

Hi @carolyn french

Thank you very much! this helps my purpose. 