The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Tasks not appearing under epics

Gary Williams
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 29, 2023

Hello, I've got an epic in JIRA and under the epic I have a bunch of tasks. 

The epic shows up in the timeline view but the tasks linked to that epic do not even though they have start and end dates set.

Is this a limitation of JIRA or something I'm missing? The project itself is a company software project.

Thank you.

 

2 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

3 votes
Answer accepted
Walter Buggenhout
Community Champion
November 29, 2023

Hi @Gary Williams and welcome to the Community!

In your Board settings / timeline, make sure you have enabled the tick next to child level issue scheduling and also select the right option to represent dates on the timeline:

2023-11-29 11_15_15-CMSD board - Agile Board - Jira.png

Hope this helps!

Gary Williams
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 29, 2023

That did it!

Thank you so much for this. I literally spent an hour trying to get this working.

Like Walter Buggenhout likes this
0 votes
Antuan Sammak
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 29, 2023

Hi @Gary Williams 

 

Welcome to the Atlassian Community!

 

1- are the tasks showing in the board view?

2- can you please confirm that the filter which your board/timeline reading from is retrieving those tasks?

3- if the answer to the above 2 questions is yes, then i would like to ask you please to provide a screenshot from your timeline view if possible to check any addition filter enabled