I created a new Sprint (Sprint 4), prior to closing the active Sprint (Sprint 3). Upon closing Sprint 3, I was not prompted to move the open Issues to Sprint 4. Now when I view the Backlog, there are no Issues listed under each of the Epics, nor in the Backlog. But yet, when I open one of the Issues, it does show assigned to Sprint 4.
It appears that your Epic and its child issues are in two different projects.
FY22DSC is the Project Key for your Epic.
FDC is the Project Key for the child stories.
What is the filter for this board? That would be found under Board Settings (the ... button) > General. Does the filter include criteria to select the issues in the FDC project?
Thank you. It does limit the view from the other project. Knowing this, I'll adjust the filter and hopefully be on my way. Thanks again.