Task driving milestones

Alasdair McKie
Contributor
August 26, 2021

Hi @Anna-BigPicture

 

We are having problems with turning something into a milestone when it has underpinning tasks/stories under it within the task hierarchy. Please could you explain why this is not possible within the system or if there is a work around?

 

Thank you, 


Alasdair 

1 answer

1 accepted

0 votes
Answer accepted
Anna-BigPicture
Atlassian Partner
August 30, 2021

Hi @Alasdair McKie

Indeed, parent tasks cannot be converted into Milestone, which results from the difference in duration of both elements.
 
By definition, milestones are represented on the Gantt chart as diamonds that do not have any duration, while parent task is a sum of the duration of its children. 
 
A good practice and recommended workaround is using an additional Jira issue (milestone) or a Basic Task to mark a specific point along a project timeline and link it with a given parent task. 
If you want to avoid litter their Jira backlog with milestones, then we recommend using Basic Task.
 
Let me know if you have further questions.

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, team '25 europe, atlassian event, barcelona 2025, jira, confluence, atlassian intelligence, rovo, ai-powered collaboration, developer tools, agile teams, digital transformation, teamwork solutions, atlassian conference, product announcements

🌆 Team '25 Europe registration is now open!

Join the largest European gathering of the Atlassian Community and reimagine what’s possible when great teams and transformative technology come together. Plus, grab your Super Fan ticket now and save over €1,000 on your pass before prices rise on 3 June.

Register now
AUG Leaders

Atlassian Community Events