The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Task creating

Салімов Ашраф Акиф Огли
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 4, 2025

Hello!

Is it possible to create the task, that will have 3 subtasks, that will create automaticly every day the same way (1 task and 3subtasks)?

Is it possible to create a task that will have 3 subtasks that will be automatically created every day in the same way? Our company needs this and we are looking for a convenient task planner.

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

4 votes
Dirk Ronsmans
Community Champion
April 4, 2025

Hi @Салімов Ашраф Акиф Огли ,

Definitely!  I guess the easiest would be to set up an Automation rule (https://www.atlassian.com/software/jira/guides/automation/overview#what-is-automation)

The trigger would be a "Scheduled" rule and then you can add the action to Create Issue for your main Task.

After that you'll use a Branch for the "most recently created issue" and create your 3 other tasks in that branch

Салімов Ашраф Акиф Огли
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 4, 2025

Hi, @Dirk Ronsmans !
Thanks a lot!