  • Target start and target end (date fields from Portfolio) treated as empty fields even they are not

Target start and target end (date fields from Portfolio) treated as empty fields even they are not

Robin
February 6, 2020

Running JQL:

"Target start" is empty

Expected result:
Only issues where the Target end-field is empty

Actual result:

Issues with target end date is also included

 

Anyone else experiencing the same issue with the date fields from Portfolio for Jira?

 

2 answers

1 accepted

0 votes
Answer accepted
Pete Singleton
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 6, 2020

I experienced this exact same problem a couple of days ago.  A re-index of the individual project cured it for me.  I would suggest a full system re-index if you are able to do that.

0 votes
Robin
March 17, 2020

Reindex solved it. Thanks