Subscriptions 2 days before a certain start date possible?

Lacramioara Rosca
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 12, 2015

I have created a JIRA filter which contains a column with the start date for different projects. Is it possible to receive an email notification 2 days before each start date if there is any in that period?

1 answer

1 accepted

0 votes
Answer accepted
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 12, 2015

You can do something like this:

"Start Date" >= startOfDay(2) and "Start Date" < startOfDay(3)

This will get you all issues with Start date as 2 days from today. You can then run the subscription early morning to get an email of all issues starting in the next 2 days. You can also add more conditions to filter the results.

PS: Make sure you replace the start date with the appropriate custom field name.

Lacramioara Rosca
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 12, 2015

Thank you! I was exactly what I needed.

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events