The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Sub Task created from Task showing as Not Linked to an EPIC

Julie Mullen
Contributor
April 12, 2023

I have created a task and linked to one of my EPICS.  I then created 4 subtasks on the Task.  2 of these have successfully showing under the EPIC however 2 are showing as no EPIC.

Below is the issue which has been linked to an EPIC.  However on my Kanban board Sub Tasks 190 and 191 are showing as not Linked to EPIC

Issue linked to Epic.PNG Any thoughts?

Sub Task not Linked.PNG

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

4 votes
Answer accepted
Alex Koxaras -Relational-
Community Champion
April 12, 2023

Hi @Julie Mullen and welcome to the community

I've managed to reproduce your issue, and this happens because your two subtasks (which appear to have no epic) are moved to another status while your Epic stayed in the backlog. Thus, no epic is visible on the kanban board. As soon as you move your epic on the kanban board (e.g. selected for dev) then these subtasks will move to a dedicated swimlane.

Julie Mullen
Contributor
April 12, 2023

Perfect - thank you very much