The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Strange burndown chart view missing ideal line (guideline)

Franz Schmidt
Contributor
October 14, 2013

Hi, I have a problem with the ideal line (guideline) in my burndown chart. It is missing and it is NOT because I add stories after the sprint started.
If I look at the Sprint log file below the burndown chart, I can see that Jira Agile used the time I 'created the Sprint' as the 'Sprint start' time. So, in this case I created the sprint at 12:00pm before the Sprint planning meeting. The Sprint backlog got filled during the Sprint planning meeting and I 'started' the Sprint at 03:00pm after the Sprint planning meeting.

IMO this is a bug or am I doing someting wrong? Time should only start ticking when I hit the SPRINT START button. Where would you suggest to file issues like these? best,

4 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

3 votes
Answer accepted
Franz Schmidt
Contributor
January 23, 2014

Easy fix is to set the start time of the sprint to a future point in time. Then everything is caluculated correctly

0 votes
Charles Liu
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 14, 2018

Yup, setting start date to past was the problem. Edit the sprint and have it start today fixed it.

0 votes
Michael Zedeler
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 7, 2014

Ditto.

0 votes
Chris Waldron
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 3, 2013

I'm having this same problem as well.

Comments for this post are closed