The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Story and Sub Task date relationship

a594141
April 12, 2017

Hello. I am using Sub Tasks in my JIRA project and I have two questions:

1- Is there a way to link the due date of the sub task to the due date of the story? If I change the sub task it would be useful for the last due date of the tasks to roll up to the story

2- Is there a way to show the due date on the story page. Currently all you see is the Summary, the Type, the Status and who it assigned to. Because the Due Date doesn't roll up to the story, you can't quickly see whether the sub task Due Dates are later than the story due date 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 12, 2017

Not natively, as there are so many different things people might want to do with fields on issues and their sub-tasks, there's no code for handling a wide generic case.  Issues and sub-tasks are separate entities, so there's no simple rules for a relationship.

You are going to need to find or write code to implement the rules you want for the due dates on the issues.

On point 2 though, yes - you can add due date to the sub-task display.  See https://confluence.atlassian.com/jira/how-to-display-custom-field-of-the-sub-task-in-the-parent-issue-screen-163939652.html