The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Story-Points in Burndown-Diagram vs. Backlog

Detlef Jockheck
September 29, 2020

I started a new sprint with about 261 story points in the current sprint. Now after a few days I took a look into the burndown-diagram and saw that this shows about 817 points. Where might this difference come from?

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Gustavo Félix
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
September 29, 2020

If you click on the peek of the burndown , do you see anything showing that the scope changed?

Detlef Jockheck
September 29, 2020

I just found the reason. Some Epics have Story-Points. I guess they should'nt have. After settings the story points of this epics to zero the burndown-diagramm shows a suitable number of story points. Unfortunally I'm not able to correct this in the past (the first week of my sprint). So the sprint started with 817 SP and fell down yesterday to 261 SP.

Gustavo Félix
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
September 29, 2020

I was pretty sure that it didn't include epics...
When you go to reports->burndownchart on the bottom of the page it shows which issues are included, if its including your epics they would show there.

I'm just curious about it. 

Detlef Jockheck
September 30, 2020

As I can see on the bottom of the page epics are included... That might be another reason. Some Epics are linked to the current sprint. I guess from the idea they should'nt belong to a sprint.

Gustavo Félix
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
September 30, 2020

I was trying to include them on the sprint and the only way I found was to edit the "sprint" field on the epic. 
Before that , my epic had story points but they didnt affect the burndown. When I add the sprint field to the epic and choose the current sprint, my burndown was affected.

Like Detlef Jockheck likes this
Detlef Jockheck
September 30, 2020

That's correct. I think the reason in my case was, that the mentioned issues have been created as storys (incl. story points). Later we saw that this is larger issue than expected. So we moved this issue from story to epic, but did'nt remove the story points.

Like Gustavo Félix likes this