The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
  • Community
  • Q&A
  • Jira
  • Questions
  • Story Point Estimates for Epic should have the option to automatically aggregate Child Story Points

Story Point Estimates for Epic should have the option to automatically aggregate Child Story Points

Venkata Babji Rao
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 4, 2020

I would be beneficial if the story point estimates for an Epic is provided with have an option to automatically aggregate Child Story Points as this will provide management 10000 foot view on the size of epics

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 5, 2020

Hello @Venkata Babji Rao

Welcome to the Atlassian Community!

Indeed, Jira does not have the functionality to sum the Story points from stories in their related Epics. We understand how useful this feature would be to better prioritize and work on your Epics, so we created the following feature request to get it implemented:

Sum Story points for epics 

Feel free to vote and watch the suggestion to increase its priority and also receive notifications about any updates.

As an option, you can use a third-party app to add that feature, as Epic Sum-Up. P.S: There is a free version for this same app, that you can use to sum the time spent on child issues.

Let us know if you have any questions. 