Sprints Automation

Razia Allen May 19, 2025

How can I automate a Sprint start and complete date. 

 

3 answers

0 votes
Dilip
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 20, 2025

Hi @Razia Allen 

Jira does not natively support full automation of Sprint start and complete dates out of the box.

workaround, you can try the script runner market place app suggested here: https://community.atlassian.com/forums/Jira-questions/how-automatically-start-and-stop-sprints-same-day-every-week/qaq-p/8689

 

0 votes
Gor Greyan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 19, 2025

Hi @Razia Allen
Seems the action type for the Start sprint is not available in the Cloud. 
There is an open task for that feature.
https://jira.atlassian.com/browse/JRACLOUD-90921

Also, you can have a look at this community discussion.
https://community.atlassian.com/forums/Automation-questions/automation-is-missing-sprint-related-actions/qaq-p/2476910

0 votes
Trudy Claspill
Community Champion
May 19, 2025

Hello @Razia Allen 

Welcome to the Atlassian community.

What exactly are you trying to automate?

Are you trying to automatically start sprints and automatically end sprints?

Are you trying to automate the Start and End dates that are specified for sprints when you create the sprint?

Razia Allen May 19, 2025

Yes so, my sprints are schedule for a two-week period (10) days --every other Monday is my Sprint Complete and Start on the same day. I want to automate this at like 1 am every other Monday. 

Razia Allen May 19, 2025

yes 

 

Trudy Claspill
Community Champion
May 19, 2025

What are you trying to automate...?

  1. The creation of sprints with a 2 week duration?
  2. The starting of a sprint on its start date?
  3. The ending of a sprint on its end date?

What would you expect to have done with the incomplete issues when a sprint was completed? Would they go to the backlog or to a the next sprint?

Typically the content of a sprint is set manually. If you are trying to automate creation of sprints, how is the content of that sprint going to be set?

Do you run multiple sprints at one time in the Scrum board?

 

Why are you trying to automate this? What is the root problem you are trying to solve where doing these tasks manually is undesirable?

Razia Allen May 19, 2025

My manager asked me to look into if this process can be automated. 

On the sprint completion date, the issues not done will move into the new Sprint. 

Razia Allen May 19, 2025

The new Sprint will also start once the old Sprint is completed 

Trudy Claspill
Community Champion
May 19, 2025

Why is managing the ending and starting of sprints manually a problem?

What problem is your manager trying to solve by having the process automated?

 

It may be possible to do, but it may not be worth the effort or it may not solve the real problem.

I find it valuable to get a clear understanding of the problem the person wants resolved to assess if the solution they are proposing is going to be effective.