The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Sprint report missing tickets - has this ever happened to anyone before?

Kathy Burgess
May 10, 2023

Hi All 

We take a snapshot at the start of every sprint ( aka - we download a sprint report in the form of a csv) and upload it to an ISO repository as evidence of what was committed ( and later completed) in each sprint.   In a recent sprint, it was observed that the export was missing some tickets.  I went back and reviewed the history of the tickets and they were added before the export took place.   I also reviewed the date of the extract -- after the tickets were added.   

Has anyone ever had this happen?  Any ideas as to why this could happen?

I have been doing this for at least 2 years now and it has never before occurred 

Thanks 

Kathy

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Brant Schroeder
Community Champion
August 22, 2023

@Kathy Burgess I would suggest reviewing the report at the time you make the export.  This way you should be able to track down what is happening.  I would have guessed that the issues were not in the sprint at the time of the export but sounds like that is not the case.