Hi guys,
I am not sure if someone already encountered this. we have 1 board and I was checking something and found that the dates in the sprint cycles overlapped with the next sprint.
When I edit the sprint cycle, its not showing the same date (For example on image above, Sprint 25.25 starts on Dec9-24 in backlog view but when you edit, it shows Dec10-24).
When I checked with other admins, their view is correct...
Both Images are of the JIRA project.
Is there any settings on my account to fix this?
The most common cause of your problem is a time zone mismatch between your personal Jira account and the rest of the team/site.
You can try update your time zone by following these steps:
Click your profile icon in the upper-right corner of your Jira dashboard.
Select Account settings.
Open the Account preferences tab.
Find the Your time zone section and click the drop-down menu.
Choose your correct time zone from the list.
After updating your time zone, please check again to see if the issue persists.
Hope it helps 🙌