The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Sprint Disappears

ChuckV
April 17, 2014

Question regarding Sprints in Agile 6.1.6 Do sprints automatically end when the stop date/time occurs? I have had sprints disappear that still had active tasks...the tasks are stuck in the sprint and I am not able to move them to the backlog.

2 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Anna Cardino
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
April 24, 2014

Hey there, Chuck.

When you mentioned that the sprint disappeared, did you double check in the AO_60DB71_SPRINT table whether the Sprint is still present? Under the CLOSED column, is it still showing f or t?

Also, does it occur in a specific Scrum board or is the same behaviour observed in other boards as well? As far as I am concerned, the Sprint will not be closed abruptly even after you reach the End Date. The sprint will be closed after you completed the sprint as per the following link below:

https://confluence.atlassian.com/display/AGILE/Ending+a+Sprint

By default, any incomplete issues should be moved back to the Backlog. So, this is definitely a strange behaviour.

0 votes
ChuckV
April 29, 2014

user error