The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Sprint Carry-over issue

jira_admin_cu
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
September 8, 2020

Hi Team,

We are currently utilizing the sprint feature in JIRA, and when we go to close out a sprint, we add the tasks not completed to the upcoming sprint. However, it appears some of those are being missed and updated to the new 'Sprint' value. Could anyone please suggest on this ?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
September 8, 2020

You can set Jira to do this automatically - close sprint, all issues that are not "done" will move. 

How are you moving issues to the upcoming sprint?