The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Sprint Backlog - only 5 closed tasks should shown on the board

Judith Straller
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 17, 2020

hi everyone,

do you know if there a setting where I can only display a certain number of completed tasks in the sprint backlog?

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Jack Brickey
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
September 17, 2020

you can't restrict the done column to a number but can age issues off after x-days of being done. for that just change your board's filter to exclude resolved issues older than 5 days for example

... AND resolveddate >= startofday(-5d)

Judith Straller
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 17, 2020

thanks a lot for your answer Jack!