The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Setting due date JQL basing on created date

Ta Minh Thuy
August 13, 2020

Hello all,

I'm strugging with writing a JQL using due date.

I used JIra mics workflow to automatically set due date for the issue when it is created 5 days and nobody starts working on it yet.

Automated Due Date based on Create Date (+5 Days)

 

Now I need to create a filter to list all issues that have Due in less than 3 days & Due passed 3 Days - 14 Days.

Please help!

 

 

 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
John Funk
Community Champion
August 13, 2020

Hi @Ta Minh Thuy ,

If you use: project = ABC and duedate <= startOfDay(3) and statusCategory != Done

that will show you everything that is already past due or due within the next 3 days. 

Ta Minh Thuy
October 29, 2020

Thank you so much Mr. John!