I have separate workflow for stories and tasks. Both have different "completed" statuses (story - deployed, task - done). As far as I know there may be just one green column on board. So if the stories' column is at the end it works fine because story points above turn from blue to green and I can track progress. But I cannot close sprint as Jira says that subtasks are not completed. However, when I set the tasks' column at the end I can close sprint but I have 0 story points and it looks like nothing has been done. 

What is the solution?

Thanks a lot

3 answers

2 accepted

2 votes
Answer accepted
Walter Buggenhout
Community Champion
November 15, 2021

Hi @Magda Michalak and welcome to the Community!

Just map the done statuses of both your task and story workflow to the rightmost column of the board.

If your project is team-managed, you can do so from Project Settings -> Board. In a company-managed project, this is from Board Settings -> Columns.

Hope this helps!

1 vote
Answer accepted
Jack Brickey
Community Champion
November 15, 2021

Hi Magda, welcome to the community. Are you using a CMP or TMP project? Regardless, you should be able to put both done statuses into the last column. Example below for TMP

2021-11-15_09-46-08.jpg

0 votes
Magdalena Michalak
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 15, 2021

Thank you sooo much for quick response! Of course that works. The darkest place is under the candle... :D