The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Script for updating the field

Ramesh Krishnan
Contributor
November 4, 2025

Whenever status changed from "To Do" to "In progress" for EPIC, then update or assign the default value for story point as 1 and Priority as Medium. For this use case, i need automation script.

2 answers

2 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

4 votes
Answer accepted
Karan Sachdev
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 4, 2025

Hey @Ramesh Krishnan

You may create a rule like below:

Trigger:

  • Work Item Transitioned:
    • From:To Do
    • To: In Progress
  • Condition:
    • IF: Work type : Epic
  • Action:
    • Edit Work Item:
      • Story Points: 1
      • priority: Medium

If you've already created a rule but it's not working as expected, please share the details so we can suggest the next steps.

Thanks!

1 vote
Answer accepted
Nikola Perisic
Community Champion
November 4, 2025

Hi @Ramesh Krishnan 

You can follow the steps from the screenshot

Screenshot 2025-11-04 at 16.45.27.png

Ramesh Krishnan
Contributor
November 4, 2025

it works fine. thanks for the guidance