No stories were added to the Sprint once it started, however, there was a scope change of 2,800% showing on the Sprint Health Gadget which I display on my Project Dashboard!
Does someone have any suggestions on what might be wrong. Thanks!
Hi @Chino M -- Welcome to the Atlassian Community!
If you check other posts in this community, you will see others observed this symptom when the Start/End Date and Time for the sprint configuration is different from when the sprint was started (or completed). This could result in detecting some of the issues in the sprint as scope change.
Best regards,
Bill
Yes, you are right. The proposed start time for the sprint was an hour earlier than the actual start time. Thank you @Bill Sheboy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
i have added this kind of Health Gadget in my chlordioxidlösung website its not working can someone help me thank you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.