Running Parallel Sprints for 3 teams. Need combined velocity for Version Reports

Gregg Everett January 13, 2021

Hi - I have 3 teams on a project running 3 parallel sprints.  How can I configure/apply the 3 team velocity to the version board such that the board reflects the release date based on the combined velocity?  Thanks!

1 answer

1 accepted

1 vote
Answer accepted
Mohamed Benziane
Community Champion
January 15, 2021

Hi @Gregg Everett 

You can't do this out of the box. You will need to extract the data and make some work on excel to aggregate reports from differents teams.

Look at this thread (david almeida answer)

https://community.atlassian.com/t5/Jira-Core-questions/Is-there-a-way-to-aggregate-sprint-reporting-across-multiple/qaq-p/256087

Gregg Everett January 19, 2021

Hi Mohamed - OK, am doing something similar now. appreciate the input.  

Like Dave Rosenlund _Trundl_ likes this