Could someone explain to me please how roll up dates work in Jira.
I do not have start date field. Only due date field. Based on what does the system calculate rolled up dates. Could somebody explain it looking at my rooled up dates?
Hi @BenWade
See What are roll-ups in Advanced Roadmaps? for more info.
The latest Due Date of the standard/base issue type should roll-up to the "Epic" level.
Due dates of the "Epic" issue type should roll-up to the level above (as defined in the issue hierarchy).
This looks like:
Did you catch the news at Team ‘25? With Loom, Confluence, Atlassian Intelligence, & even Jira 👀, you won’t have to worry about taking meeting notes again… unless you want to. Join us to explore the beta & discover a new way to boost meeting productivity.
Register today!Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.