We'd like to add testing work as sub-tasks of Bugs. When the developer is done implementing they'd Resolve the parent and then the QA person would start their subtask. However, Jira does not allow you to Resolve a parent if any of its subtasks are unresolved. Is there a way to change this?
Community moderators have prevented the ability to post new answers.
You might have the subtask blocking condition added on the workflow of Bugs. Can you check after removing that condition?