Reopening a closed SPRINT

richard.barber110 August 4, 2021

One of the Team members has closed 3 of the proceeding sprints.  I looked in help and have enabled concurrent SPRINT but still get the error message below:

Cant open sprint.JPG

2 answers

2 accepted

1 vote
Answer accepted
Mikael Sandberg
Community Champion
August 4, 2021

Hi @richard.barber110,

Welcome to Atlassian Community!

Based on the information you have given you are most likely running into the third complex scenario described in this KB, Reopen a sprint.

Scenario details

  • You closed Sprint 1, and there were no completed issues in it.
  • All incomplete issues were moved back to the Backlog.
  • During sprint planning, you moved all of these issues to the future sprint, Sprint 2.
  • You started Sprint 2, and Sprint 2 is a currently active sprint when you try to reopen Sprint 1.
  • The Parallel Sprints feature is enabled.

Expected result
Sprint 1 cannot be reopened because all of its issues are now in the currently active sprint, Sprint 2. 

richard.barber110 August 7, 2021

Thanks Mikael, the scenario captured the issue and we know to better manage our issues now :-)

0 votes
Answer accepted
Melo
Community Champion
August 4, 2021

Hi Richard, and welcome to the community!

It seems like you want more than one active sprint in Jira. To accomplish that, you need to enable parallel sprints.

Here is the Atlassian documentation on how to enable it: https://support.atlassian.com/jira-software-cloud/docs/use-parallel-sprints/

I hope that helps.

Cheers,

Melo

richard.barber110 August 7, 2021

Thanks Melo, small software switch, huge impact to functionality!

Like Melo likes this