The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Remove story point field filling requirement for sub tasks.

GZ
August 26, 2021

I put validation for story points so user can not move tickets from to do to in progress without filling story point field, now when user creates sub-task it is applied for sub-tasks too, can I remove that rule/validation from sub-tasks so that user can move sub-tasks without filling sub-tasks story points field.   

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Answer accepted
Jack Brickey
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
August 26, 2021

Yes. You need to associate a different workflow to the subtask issue type.

  • copy the workflow and name it
  • edit the copy under the inactive workflows
  • remove your validators and any other desired changes
  • back in your project workflows screen Add workflow - existing 
  • find your new workflow and select it and associate to your subtask issue type
GZ
August 26, 2021

Thank you very much!