Hi

 

Time left shows 2h when 6h is logged but the estimate is 2 days. Why?

 

Link to issue https://bytskruv.atlassian.net/browse/SB-1836

 

1 answer

1 vote
Ollie Guan
Community Champion
June 4, 2019

Hi @Magnus Johansson ,

How do you define work time per day in time tracking?

pls check Time tracking settings - > Working hours per day.