Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Record Sprint Points

Damjan Majstorovic
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 1, 2014

Hi, 

is there any place in JIRA Agile, perhaps within the Reports section, where you can find the number of actual points that have been completed within the past sprints. 

In other words, my current sprint shows the actual number of points within blue/yellow/green circles (shown in the attached file). I say actual because I do not mean only the points at the start of the sprint, but the once that were added during the sprint. After I close the sprint, are these points recorded anywhere else where I can see them?

Thanks

 

 

 

plan-points.png

 

3 answers

0 votes
Damjan Majstorovic
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 1, 2014

Hi Ollie, thanks for the reply, but that is not correct. First, from that page:

  • The values for each issue's Estimate are recorded at the time the sprint is started. Changing the Estimate value afterwards will not be reflected in the Sprint Report.

For example in my sprint that I posted above I should have 230 points, on Sprint Report I have only 100.


Thanks

Damjan 

0 votes
Ollie Guan
Community Champion
November 1, 2014

Suggest an answer

Log in or Sign up to answer