Progress Summary in Timeline & List Views Similar to Product Discovery

Amanda Manley May 20, 2025

In JIRA Product Discovery, I really appreciate the visual summary of delivery ticket progress- it shows how many items are To Do, In Progress, and Done, both as a progress bar and in numeric form. This makes it easy to assess delivery progress at a glance.

I’m wondering:

  1. List View: Is there a way to replicate this type of progress summary in the standard JIRA List View?

  2. Timeline View: In Timeline View, I typically view issues at the Story level, each of which contains several subtasks. I’d love for the timeline bars to reflect progress—e.g., showing how many subtasks are complete. Is there a way to enable this, or is there an alternative view or method I should consider?

Goal:
I’d like to be able to quickly visualize progress on Stories and their subtasks directly from Timeline or List views—similar to what Product Discovery offers.

Thanks in advance for any guidance!

1 answer

0 votes
Mendel Liang
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 20, 2025

Hi Amanda,

Have you considered using the Plans Timeline view if you have Jira Premium? Plans has both a timeline and list view, and also supports a calculated field called "Progress" (either in estimate by time/story points or child work item count).

Screenshot 2025-05-21 at 2.32.20 pm.pngScreenshot 2025-05-21 at 2.30.15 pm.png

Unfortunately i'm not aware that the Timeline view in Jira Projects or the List view support this particular field.