Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Progress Reporting

Walter O_Brien-Gilbert
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 7, 2021

Hello, 

I have created a number of issues for the project and assigned start and due dates for each task which are sitting in the "In Progress" category. 

How can i assign a % complete against the progress to establish how much has been done or is there another means of establish extent of work complete whilst in progress. 

Thanks 

2 answers

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 7, 2021

Obviously, you will need to get people to enter data into Jira that you can use to report on a percentage, but the first question has to be "a percentage of what?"  Time elapsed?  Time spent working on it?  Number of sub-tasks done?  Movement through process steps?

You could just ask people to fill in a simple numeric field for a flat percentage (or, safer, a dropdown for say 0, 25, 50, 75), but that doesn't really tell you much because there's no actual measurement underneath it, your people are mostly just guessing, and worse,  it's a faff to have to remember to update it, so generally people won't bother - you'll end up with 0% for not started, 100% for done and mostly 0% for everything else unless you force them to enter something, at which point you can expect to see a lot of 50%s or random numbers that won't tell you anything more than "we're working on it"

Walter O_Brien-Gilbert
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 11, 2021

Hi Nic, 

 

Thanks for the revert. The intent was to look at % complete on an activity. ideally what i am looking for is physical % complete. Each task will clearly have an effort and time allocation to which we could be a 100% on the time but only achieved 50% of the work. 

If i can establish physical % complete, i can take a view of an estimate to complete, what is needed to complete the work in the scheduled time. Through this i can establish to what extent i need to calibrate activities or how hard i need to drive the completion of the tasks dependent on criticality.   

If there is no direct input area in Jira, its fine. New to Jira so had some expectations but will have to adopt other methods. 

 

Thanks for the input. 

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 11, 2021

"A physical % complete" is not any more descriptive than just "a %".  What are you measuring for completion?

0 votes
Sai_ManageEngine_AnalyticsPlus
Atlassian Partner
March 2, 2021

Hello Walter,

If you're looking for a ready-to-use reporting solution for Jira Software, you can try the Analytics Plus app. It comes with several prebuilt reports like the one below that enables you to track the percentage completion of issues at a glance, and also gives you a forecast of issues that will be completed in the future.

6890358a-6701-483d-a723-0663020a9a79.png

Using Analytics Plus, you can,

  • Track progress of tasks, issues, epics, and more using prebuilt reports.
  • Predict, plan and map out project plans accurately.
  • Assess the complete project in a single dashboard to spot and troubleshoot bottlenecks.
  • Compare past project plans and completion schedules to measure the effectiveness of your project plans
  • Tag other stakeholders and discuss project plans from within the app.

Disclaimer: I'm a product expert for Analytics Plus app.

https://marketplace.atlassian.com/apps/1223951

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
FREE
TAGS
AUG Leaders

Atlassian Community Events